美国留学生项目管理专业毕业dissertation格式模板下载-Schedule Management & Control
工作分解结构(WBS)是工作内容的分层表示。它被证明是有效的,使用WBS的定义和结构工程。WBS现在是项目管理中的一个共同的工具,项目管理知识的书(PMBOK)收集和重新定义它的话。根据PMBOK的描述,WBS是一个可交付成果导向的层次分解的工作将由项目团队执行(PMI,2008)。通过项目WBS,又可细分为更小的部分,为了让项目经理或其他人员对项目要素明确。同时,它可以使操作程序标准化的一大贡献。
在1917年由亨利·劳伦斯·甘特发明的甘特图。甘特图的形式是一种棒图。以棒图,横轴表示的持续时间,而垂直轴代表在项目中的那些任务。在图表中的单杠,给人以视觉上的形象,以飨读者了解每个任务的条件。单杠的长度可以显示的任务应该花多长时间的酒吧的开始和结束的时间点的任务的开始和结束。甘特图是由任务持续时间的关系附件和时间尺度。
3. Overview of Schedule Management Tools
3.1 Work Breakdown Structure (WBS)
Work breakdown structure (WBS) is a hierarchical representation of the work contents. It is proved to be efficient that using WBS to define and structure the project works. WBS for now is a common tool in project management as the Project Management Book of Knowledge (PMBOK) collected the word and redefined it. According PMBOK’s describe, WBS is a deliverable oriented hierarchical decomposition of the work to be executed by the project team (PMI, 2008). Through WBS, the project can be subdivided into smaller parts in order to let project managers or other workers clear about the components of the project. And also, it can make a great contribution to operate procedure standardization.
The importance of Work Breakdown Structure has been acknowledged by both theoretical researchers and engineering practice personnel. First of all, tt is the basis for defining work packages which is the crucial work of project management preparation (Rad, 1999; Colenso, 2000). Garcia-Forniels et al. (2003) declared that the WBS is the most important tool for project management because it provides a basis for scheduling, planning, responsibility assignment, information management and control. Also, through the procedure of WBS, the construction project information can be collected by the computer. Thus the WBS is the fundamental of project informationize.
Being a kind of scientific methodology of project management, the process of decomposition lead by WBS is not arbitrary but according to a sequence of principles and standards. There are 3 most important pre-works need to complete before project managers initiate the WBS process. The first relates to the decomposition criteria, which reflect the facets of information by which the work is subdivided across the WBS hierarchy. The second is the sequencing of these criteria, which relates to the order in which the criteria are applied in the hierarchy. The third issue relates to the level of detail, which reflects the extent to which the entire work is decomposed.#p#分页标题#e#
Meanwhile, there are another 3 principles should be followed:
1) Each hierarchy should be a complete reflection of the whole project.
2) Different hierarchy should have different standard when decomposition.
3) The amount of hierarchies should stay at a proper level that those tasks in the lowest hierarchy can be precisely evaluated.
3.2 Gantt Chart
Gantt chart is invented by Henry Laurence Gantt in 1917. The form of Gantt chart is a kind of bar diagram. In the bar diagram, the horizontal axis represents for the duration and the vertical axis represents for those tasks in the project. The horizontal bar in the chart gives a visual image to readers to understand the condition of each task. The length of the horizontal bar can show how long the task should spend; the start and the end of the bar represent the time point of the task starts and ends. Gantt chart is composed by task duration, line of relationship attachment and time scale.
Gantt chart is used widely in project management. According to the describe of Gantt chart which is stated before, the biggest usage of Gantt chart is that it can provide an overview of the project activities and their inner relationships and then to make a plan. Furthermore, using Gantt chart can also make analysis about the whole schedule plan, such as critical path calculation and total duration evaluation. In project operation stage, Gantt chart is also a useful tool in order to draw a clear conclusion about the deviation between the planned schedule and the recent one. To identify this kind of deviation is the foundation of adjustment, so as to keep the project run to the right way.
Compared with other schedule plan techniques such as PERT, there are several benefits when using Gantt chart. First of all, when dealing with small and medium sized projects, it can provide an excellent graphic image which is much easier to understand. Second, Gantt chart can be supported by some special project management software to realize complex calculations and complex dependencies and conduct “what-if” analysis (Harvey, 2011).
However, as a kind of primary project management tool which is developed for such a long time, Gantt chart has some limitations when dealing with complex problems. Especially for this modern society, more and more complex projects appeared. They are often considerably more complex than can be communicated effectively by a Gantt chart. Moreover, Gantt chart only represents few parts of project management field. It mainly focuses on schedule management but according to PMBOK, project management is composed by nine parts. And there are some researchers argued that Gantt chart do not represent the size of the project or the relative size of work elements, therefore the magnitude of a behind-schedule condition can be easily misunderstood (Stephen, 2011).
3.3 Program Evaluation and Review Technique (PERT)
Program Evaluation and Review Technique (PERT) is a kind of useful technology which is used in schedule planning and optimizing. It is developed in the late 1950’s for the US Navy’s Polaris project which had thousands of contractors. Based on the duration and the precedence relationship of those tasks, it can optimize the total duration and make a proper arrangement about each task’s position in the whole schedule plan.#p#分页标题#e#
PERT is focus on the mile stone task (or time point) and the critical path which is consisted of a series of tasks that direct related to the total duration. The mile stone event represents some key points in schedule management that in these key points, to compare with the planed performance and the real one will let the project manager know exactly the project’s progress and potential risks. Those tasks in critical path should not be changed easily because a slight change will cause the whole schedule plan facing readjust risk. Of course on the other hand, to short the duration of tasks in critical path is the only way to short the whole duration of project. In addition, it should be stated that not like the Gantt Chart, those task durations in PERT are all expected value but not a precise pre-evaluation. So, the real value of duration is uncertain which means in the project management practice (Maria etc., 2011), readjustment should be considered first in the schedule planning.
PERT consists of several steps to complete a project plan. First of all, and also the fundamental of PERT process is to identify specific activities, the inner relationships between each tasks and milestones. This step is always done by WBS. The second step is to construct a network diagram. It has two major methods, Activity on Node method (AON) and Activity on Arrow method (AOA). AON method use nodes to represent tasks and arrows represent precedence relationships only. AOA method use arrows to represent tasks and the position of arrows represent precedence relationship. The next step is to estimate the time coefficients of each task. The time coefficients mainly include ES (earliest start time), EF (earliest finish time), LS (latest start time), LF (latest finish time), FF (free float) and TF (total float). The forth step is to determine the critical path. Commonly those tasks with zero free float are in the critical path. The last step is to update as project progresses. As it is stated before, the expected value of duration will be replaced by the real one in project management practice, so the PERT chart should be modified to cope with the new situation.
The benefits brought by PERT is obvious:
1) PERT promotes identification of the critical path and makes this visible for managers.
2) PERT promotes identification of late start, early start, and slack (free float and total float) for each task.
3) a PERT chart exactly defines and makes visible precedence relationships between the tasks identified by WBS.
4) PERT provides for potentially reduced project duration due to better understanding of precedence relationships leading to improved overlapping of tasks where feasible.
And also, there are some limitations exist when using PERT chart:
1) The accuracy of PERT is mainly based on the task identification which is done by WBS and the estimation of task duration. However, there can be potentially hundreds or thousands of activities and individual dependency relationships which can have large influence on the result of PERT chart.#p#分页标题#e#
2) The lack of accurate timeframe on most PERT charts makes it harder to show status. And furthermore, some experts said that PERT over emphasized the critical path (Davaadorjin, 2010).
3) Just like Gantt chart, when the PERT charts become unwieldy, they are no longer used to manage the project.
. Task Identity by WBS
4.1 Decomposition Criteria
The set of decomposition criteria is the first difficult task when using WBS. In order to standardize the business process of WBS in construction area, a lot of organizations and individual researchers put forward their thoughts. The International Organization for Standardization (ISO, 1994) identified eight factors of classification for construction information. These include space (office spaces, recreational, etc.), facility (school, hospital, etc.), work section (masonry, concrete work, etc.), element (floors, stairs, etc.), construction aid (scaffolding, formwork, etc.), construction product (cement, paint, etc.), management (procurement, drawing, etc.) and attributes (size, shape, etc.). These facets were updated in ISO (2001) to include more classes. The ones relevant to this study are construction complexes (industrial complex, transport complex, etc.), construction entities (bridges, buildings, etc.), life cycle phases (production phase, design phase, etc.) and work results (filling, excavation, etc.).
相关文章
UKthesis provides an online writing service for all types of academic writing. Check out some of them and don't hesitate to place your order.