项目管理方面留学生课程essay写作-Sopwith Aircruiser
Introduction
The Sopwith Aircraft Industries (SAI) has a long tradition of aircraft manufacture. SAC is planning the development of a new passenger aircraft: Sopwith Aircruiser 3 (SAC 3). The SAC 3 is intended to have a larger capacity and offer greater fuel efficiency than the current SAC 2. A number of options have been considered and just two remain as serious possibilities: the radical SAC3a and the SAC 3b which is a more conservative development of the successful SAC 2. Given the well publicised problems with some competitors’ major aircraft developments, SAI have requested a risk analysis of the project and the options. 该塔飞机工业(SAI)具有悠久传统的飞机制造。囊是规划一个新的客运飞机的发展:塔aircruiser 3(SAC 3)。囊3是为了有一个更大的容量和提供比当前的SAC 2燃料效率更高。一些选项已经被认为是和两个仍然是严重的可能性:激进的sac3a和囊3b,是一个较为保守的发展成功的囊2。鉴于广泛宣传的问题与一些竞争对手的大飞机的发展,西有要求的项目的风险分析与选择。
The programme for the development of the SAC 3 is dominated by design and testing: it is well worth spending more time and money getting the design right, even if it does appear to delay the whole programme. Solving problems later is very expensive. Computer simulations are used extensively at the design stage to explore alternatives and assess the options. Good design should require relatively little modification. However, the stringent safety requirements imply a rigorous regime of testing. Inevitably some modifications will be needed but past experience suggests that these should be manageable and not introduce substantial delays, or additional costs.
If the SAC 3 development is approved by the Board of Directors, work on the project will begin in June 2011.
Task
You have been asked as a project management consultant to help SAC assess whether the SAC3 development is financially viable and recommend a project plan. You should produce a report for the SAI Board of Directors in time for its next meeting on 10 May 2010. The report should provide:
• a plan illustrating the logic of the project;
• an assessment of the project’s financial viability, assuming no risk;
• a qualitative risk assessment of the project proposal;
• a quantitative analysis of the schedule risk;
• a quantitative analysis of the financial risk;
• a comparison of the two options SAC3a and SAC3b;
• recommendations to the SAI Board.
A number of interviews have been held with key staff from SAI and these have been
summarised below#p#分页标题#e#
任务
你被要求作为一个项目管理顾问帮助囊评估是否SAC3发展在经济上是可行的和推荐的项目计划。你应该产生一个报告会西板在下次会议时间2010日10。该报告应提供:
•计划说明项目的逻辑;
•对项目的财务可行性评估,假设无风险;
•定性风险评估项目建议书;
•定量分析的进度风险;
•定量分析金融风险;
•比较这两个选项sac3a和sac3b;
•建议到西板。
多个面试已举行了与西关键员工和已
概述如下
.
The SAC3 options
The SAI Board are divided: some support the radial SAC3a option and others the more conservative SAC3b design. The SAC3a should offer greater performance, generating higher sales and a higher income. However, the SAC3a is dependent on a much greater use of new materials for the wings and fuselage. This should reduce weight, potentially increasing the load and fuel efficiency but it does introduce some additional risks.
The design and prototype production phase
While the design concept is well advanced, further discussions are needed with the potential airline customers and airports to confirm the concept (estimated time = 3 months, costing £20 million). Once the design concept is agreed, the detailed design of the main elements of the aircraft can begin. The main elements include:
• specifying the engine with the chosen manufacturer; while the engine will be a standard model, various modifications will be needed to meet the requirements of the SAC3 (3 months and costing £20 million)
• the design of the avionics system and the production of a prototype will take approx. 18 months and cost £100 million;
• the design of the fuselage and the production of a prototype fuselage will take approx.15 months and cost £60 million for the SAC3b option (18 months; £80 million for the SAC3a);
• designing the wings and producing the prototype for use in the test aircraft will take 15 months and cost £80 million for the SAC3b (18 months; £120 million for the SAC3a)
The aircraft interior
The design of the interior of the aircraft (12 months; £20 million) can also begin once the design concept is agreed. However there is no great urgency: the interior fittings will only be included in the adapted prototype aircraft for the second set of flight trials. Although the aircraft interior may appear to be a relatively minor component, it is important for passenger comfort, safety and the efficient operation of the aircraft. It can be difficult to specify precisely since these factors are often hard to quantify and determining aspects such as “comfort” in advance.#p#分页标题#e#
Satisfying a variety of users
Any new aircraft has to meet the demands of several “users”. It has to be attractive to the passengers, meeting their expectations for comfort and safety. The aircraft also has to meet the demands of the airlines, providing efficiency and reliability, with the capacity and range necessary for the projected routes. The aircraft also has to be compatible with the facilities provided at the various airports: the aircraft must be able to land and take off safely; the refuelling systems must be suitable; passenger embarkation and baggage handling have to be considered in order to ensure a smooth integration of the new aircraft with the existing airport operations. Apparently minor issues, such as the size of baggage doors can cause significant and costly problems. While it may not cost much (£5 million), liaison with the key airports is essential and should start as soon as the design concept has been confirmed and allow 18 months. The results of this exercise provide input into the revision of the design and construction of the adapted prototype aircraft.
Avionics systems
Avionics systems in modern aircraft are crucial. But they are becoming ever more complex involving numerous separate computer based systems monitoring and controlling a great range of aircraft functions. In addition to the technical requirements, the systems also have to provide a clears man-machine interface. Providing the flight crew with data and control is not sufficient: the information display and the controls have to be carefully organised to enable the crew to fly the aircraft. Even though the aircraft may usually fly on automatic pilot the interface must allow human crew to take over at any instance, without causing confusion which could be disastrous.
Engines
While the standard engine models will have to be modified to fit the particular requirements of the SAC3 this should not be a major problem. The engine manufacturer requires time to produce the engines but given their experience this should not be subject to any significant delay or cost overrun and these can be regarded as “low” uncertainty activities.
Full scale production facility
The prototype aircraft and its systems will be built using specialist teams in an environment more similar to a laboratory than a factory. However, a more efficient system will be needed to construct the production aircraft. The design and build of the full scale production facility (24 months; £300 million) can begin after the assembly of the test aircraft. The actual construction of the first production aircraft will not begin until the results of the second set of flight trials are available. Inevitably the construction of the first production aircraft (3 months; £80 million) will reveal some problems; past experience suggests that these should not be major and should not cause any large delays or cost overruns. Once the safety certification is obtained the first aircraft can be delivered (1 month; no significant cost).#p#分页标题#e#
Flight trials and testing
Trials and testing are the dominant themes in aircraft development. A test aircraft is assembled (6 months; £20 million) once the prototype avionics, fuselage and wings are available. The first set of flight trials can then begin. While these are expected to last 9 months (and cost £40 million) for the SAC3b option there is a high degree of uncertainty about the duration and outcome. If the SAC3a option is adopted the duration of the flight trials could be 12 months and the cost might be £60 million. Unexpected problems may be revealed: some may be quick and cheap to resolve but others could take a long time. Some problems may not be solved and could result in having to accept a reduced capability in the final aircraft. Following the first set of trials, the design will be revised and the prototype aircraft adapted (9 months; £80 million) before embarking on a second set of flight trials (6 months and £30 million for the SAC3b; 9 months and £40 million for the SAC3a). Revising the design also requires the interior design to be complete and also the liaison with the airports should be finished, providing key inputs into the final design. Assuming the second set of flight trials is successful, safety certification will follow (3 months; £10 million ).
Customer demand and finance
Market research suggests that at a price of £70 million per aircraft that the likely demand is a total of 24 aircraft per year for the SAC3b. The SAC3a could command a higher price (£75 million and sales might be 30 per year. These sales are expected to continue until 2024 when the next generation of aircraft might be available. Inevitably there is significant uncertainty about these estimates: a standard deviation of 10% might be reasonable. Currency fluctuations, the competition and the nature of the airline business could all affect both the price, sales and product life. SAI usually employs a target IRR of 15% p.a. when assessing major projects such as the SAC3. Many of the costs of an aircraft are incurred in the development phase: a new aircraft is a very capital intensive project. However, the marginal cost of the labour, materials and the various components, including the engines, bought in from suppliers used in the construction of each SAC3a is estimated to be £63 million while the SAC3b should be cheaper to build (£60 million per aircraft). The prices of these components can be agreed in advance and there should be relatively little uncertainty, though exchange rate movements could affect some costs.
Historic SAI project data and estimating uncertainty
Some specific concerns have been identified and noted in the interview reports: these should be incorporated in the risk analysis. However, in addition SAI adopt a standard approach based on experience in previous projects. Activities are designated as low, medium, high or very high uncertainty. In general, design and assembly of prototype activities are “medium”. However, in the case of the SAC3a option and the use of new materials for the wings and fuselage perhaps the relevant design activities should be rated as “high”. Flight trials are often problematic and their uncertainty must be rated to be “very high”. Building the production facility is usually relatively predictable. Interpreting these uncertainty ratings in the context of this industry requires historic data and this has been made available as an appendix。#p#分页标题#e#