PROJECT MANAGEMENT, COURSEWORK
We advise you to use Microsoft Project 2007 for this work. This is an individual assessment. All work submitted must be your own work. Any plagiarism or copying discovered will be referred to the appropriate Head of School and constitutes a serious examination offence.
You must submit a written, typed or printed version of your coursework. Electronic submission or submission on a cd-rom or on a memory stick is not acceptable. It is not necessary to word process this assignment - work completed in a fair hand is permissible. If you do word process the task(s), we may wish to examine your work or work area at any stage during or after the assessment period. So please keep any media safe and make regular backups. Disc or printer failure is not an acceptable reason for late submission. Keeping discs and other electronic media (and their copies) safe is your responsibility.
BACKGROUND INFORMATION:
This case study is based on a job run by a firm of Architects and constitutes the pre-contract programme of an estate restoration scheme. For reasons of commercial sensitivity some tasks have been deleted, had their durations changed and/or had their links altered (at the reasonable request of the project owners).
The tasks are already grouped and indented - but resource allocations have been stripped out.
The project consists of about 80 tasks (some of which are summary tasks or milestones). The objective is to prepare an estate ready for the main works to commence - but does not include the main works schedule.#p#分页标题#e# Requirements follow: Section A:
You are given the following information about the supply of resources (all work based):
First, allocate these resources to the activities as stated below (where “A”means Architect, “L” means Labourer and so on):
It is likely that some resource clashes will occur. For the first three such clashes, document * Task numbers listed above correspond with those in the MS Project source file. * With an acceptable allocation of resources (using the above tasks as guidelines for loadings), you should find that total costs are around £1 million. You should not need to extend the duration of the project. If you do - you are probably loading in too many resources on each task. Try again. * You are advised to choose the option for “Level within available slack” from the Tools, Level Resources Window and to show the baseline as a reference point via the custom pages of the Gantt Chart Wizard. You should also save the baseline between clashes so as to collect clear evidence of each clash.
* Make sure that when you add resources to tasks you do so in a way that does not change task durations. Either allocate all the resources to a task at once or add the resources and then reset the duration to it=s original value or turn off the effort driven mechanism (remember to turn it back on for later parts, though).#p#分页标题#e#
* If you decide to solve clashes manually then remember that is it better to add new links between tasks rather than “dragging” them forward. Adding new links does not set SNET constraints that may, later, cause you problems. * You must explain carefully and fully how either Project (or you) resolved these clashes at task level. You should provide suitable evidence of the changes.
* You are advised to save versions of the file (with different names) at key points. In general, save your work frequently.
* You may add other resources if you wish .... provided that you justify their inclusion. |